1.  Disconnect the negative battery cable. (See NEGATIVE BATTERY CABLE DISCONNECTION/CONNECTION [SKYACTIV-D 2.2].)

2.  Discharge the refrigerant. (See REFRIGERANT CHARGING.)

3.  Disconnect the connector.

am3zzw00017777

4.  Detach the fastener.

5.  Remove the bolts.

6.  Remove the clip.

7.  Set the PCM out of the way.

am3zzw00014084

8.  Disconnect the refrigerant pressure sensor connector.

am3zzw00014085

9.  Remove the nut.

am3zzw00014086

10.  Remove the bolts.

11.  Remove the brackets.

12.  Set the PCM out of the way.

am3zzw00014087

13.  Remove in the order indicated in the table. Do not allow compressor oil to spill.

Caution
•  If moisture or foreign material enters the refrigeration cycle, cooling ability will be lowered and abnormal noise will occur. Always immediately plug all open fittings after removing any refrigeration cycle parts to keep moisture or foreign material out of the cycle.

am3zzw00014088

1
Cooler hose (LO)
2
Cooler pipe
3
Cooler hose (HI)

14.  Install in the reverse order of removal.

15.  Perform the refrigerant system performance test. (See REFRIGERANT SYSTEM PERFORMANCE TEST.)


Refrigerant line installation note (1)

1.  Apply compressor oil to the O-rings and connect the joints.

2.  Tighten the joint bolt by hand.

3.  Connect the block joint type pipes by grasping the female side of the block with pliers or similar tool and holding firmly, then tighten the connection bolt or nut with a torque wrench.

am6xuw00006111


Refrigerant line installation note (2)

1.   After replacing the refrigerant line, add compressor oil to the refrigeration cycle.

•  After replacing the cooler hose (HI)
Supplemental oil amount (approx. quantity)
―  1 ml {1 cc, 0.03 fl oz}
•  After replacing the cooler hose (LO)
Supplemental oil amount (approx. quantity)
―  3 ml {3 cc, 0.1 fl oz}
•   After replacing the cooler pipe
Supplemental oil amount (approx. quantity)
―  1 ml {1 cc, 0.03 fl oz}


R.H.D.

1.  Disconnect the negative battery cable. (See NEGATIVE BATTERY CABLE DISCONNECTION/CONNECTION [SKYACTIV-D 2.2].)

2.  Discharge the refrigerant. (See REFRIGERANT CHARGING.)

3.  Remove the engine cover. (See ENGINE COVER REMOVAL/INSTALLATION [SKYACTIV-D 2.2].)

4.  Remove the nuts from underside of vehicle.

am3zzw00014093

5.  Remove the nuts from top side of vehicle.

am3zzw00014094

6.  Remove the insulator as shown in the figure.

am3zzw00014095

7.  Disconnect the connector.

am3zzw00017778

8.  Detach the fastener.

9.  Remove the bolts.

10.  Remove the clip.

11.  Set the PCM out of the way.

am3zzw00014097

12.  Disconnect the refrigerant pressure sensor connector.

am3zzw00014098

13.  Remove the nut.

am3zzw00014099

14.  Remove the bolts.

15.  Remove the brackets.

16.  Set the PCM out of the way.

am3zzw00014100

17.  Remove in the order indicated in the table. Do not allow compressor oil to spill.

Caution
•  If moisture or foreign material enters the refrigeration cycle, cooling ability will be lowered and abnormal noise will occur. Always immediately plug all open fittings after removing any refrigeration cycle parts to keep moisture or foreign material out of the cycle.

am3zzw00014101

1
Cooler hose (LO)
2
Cooler pipe
3
Cooler hose (HI)

18.  Install in the reverse order of removal.

19.  Perform the refrigerant system performance test. (See REFRIGERANT SYSTEM PERFORMANCE TEST.)


Refrigerant line installation note (1)

1.  Apply compressor oil to the O-rings and connect the joints.

2.  Tighten the joint bolt by hand.

3.  Connect the block joint type pipes by grasping the female side of the block with pliers or similar tool and holding firmly, then tighten the connection bolt or nut with a torque wrench.

am6xuw00006111


Refrigerant line installation note (2)

1.   After replacing the refrigerant line, add compressor oil to the refrigeration cycle.

•  After replacing the cooler hose (HI)
Supplemental oil amount (approx. quantity)
―  1 ml {1 cc, 0.03 fl oz}
•  After replacing the cooler hose (LO)
Supplemental oil amount (approx. quantity)
―  3 ml {3 cc, 0.1 fl oz}
•   After replacing the cooler pipe